CROSSBOW HLU2-UC1-TC1 measurements: Substation measurements gathered during curtailment activation

<p>The data comprises the measurements read at the Konjsko substation before, during and after a curtailment in Pometeno Brno plant.</p> <p>The measurements gathered from the SCADA are:</p> <ul> <li>P, Q and V of the 110, 220 and 400 Kv buses at the substation</li> </ul> <p>P, Q and V of the line connecting the substation with the plant</p>

ShareScore

48/100

Overall dataset sharing score

Score breakdown

These five areas show where the dataset supports — or may limit — practical reuse.

Stewardship
8
Harmonization
4
Access
20
Reuse readiness
8
Engagement
8